When is the best time to build a pool?

The best time to start is autumn. Starting in September to November leaves time for the licence and a winter build, so in most years the pool is finished by late spring, before the summer and before construction work is restricted in many tourist areas.

Infinity pool edge meeting the sea with hills beyond

Working back from summer

Most owners want to swim by June. The licence can take time, the build takes eight to fourteen weeks on site, and the shell needs weeks to cure. Working back from June, that points to a first visit in late summer or autumn and a start on site in winter.

Infinity pool with chairs on the edge and the open sea beyond

Want to swim by next summer? Contact us in the autumn and we will plan the timeline.

Ask on WhatsApp

Why winter suits building

The weather on the Costa Blanca in winter is mostly dry and mild, which suits concrete and rendering. Crews and machines are available, neighbours are often away, and the noisy work of digging and breaking rock is done before the summer season.

Starting later

A spring start is still possible, but the pool may not be ready until later in the summer, and some urbanisations limit noisy work in July and August. If you are late, we can sometimes speed things up with a membrane finish, which is quicker than porcelain. See the stages of a pool build for the stages.

A sample calendar

WhenWhat happens
September–OctoberSurvey, design and fixed quote
October–DecemberLicence application with the council
January–MarchExcavation, shell and curing
March–MayFinish, coping, terrace and start-up
JuneFirst swim

The licence stage varies most. If it is quick, the build starts earlier and finishes with time to spare.

Weather and building

Winter on this coast is mostly mild and dry, which suits concrete work. The exceptions are the heavy autumn storms (the DANA or gota fría), which can bring a lot of rain in a few days, usually between September and November. We avoid having an open excavation during forecast storms where we can, and protect the shell and the site when we cannot. Gunite is not sprayed in heavy rain or on the rare cold mornings when frost is likely inland.

Renovations have a different calendar

A renovation doesn't need a full licence or a long build, so it can be done later. A membrane relining takes about a week from draining to refilling, and new mosaic or porcelain takes a few weeks more. Owners who use the pool in summer often book them for late winter or spring, so the pool is ready by Easter. Near the beach, the groundwater level matters too; see groundwater and pools.

High season rules in tourist areas

Several towns along this coast restrict noisy building work in the peak summer months, and many urbanisations have their own rules on working hours and machinery. The details vary by town and change from time to time, so we check them for your area when planning. Even where work is allowed, digging and breaking rock next to neighbours on holiday is best avoided. Planning the noisy stages for autumn and winter keeps everyone happier.

Booking ahead

The busiest time for enquiries is spring, when owners arrive for Easter and decide they want a pool for the summer. By then, most winter build slots are taken and the licence alone may push a start into summer. Owners who contact us in late summer or autumn get the widest choice of start dates. If you are buying a villa, ask for a survey before you complete; see adding a pool to a resale villa.

Timing is the first thing we plan for any new pool.

Read next

Questions we are asked

Can you build a pool in summer?

Yes, but it is less comfortable for neighbours and some areas restrict noisy works in high season. Most clients prefer to swim in summer, not build.

How early should I contact you?

For a pool by June, ideally the previous September or October, to allow for the licence.

Is it cheaper to build in winter?

Prices are similar through the year, but in winter it is easier to book a start date that suits you, and the pool is ready for the whole summer.

What if I only decide in spring?

We can still build, but the pool may be ready later in summer. A membrane finish and a quick licence help shorten the timeline.

Jávea Pools

Plan your timeline

Message us now and we will tell you when work could realistically start.

Mosaic infinity pool with palm shadows and the sea beyond the rooftops
WhatsApp us about your pool